Data center power availability by market

Eight US markets in one dated table: the utility, its large-load terms, published waits, vacancy, the state sales tax exemption and local limits. Every cell carries its source. Where our sources say nothing, the cell says so.

Sources rechecked in November 2026

Eight markets, side by side

Read across a row to see why a market is easy or hard to build in today. On a phone, each market reads as its own block.

MarketUtility and gridLarge-load termsWait or queueVacancyState sales tax exemptionLocal rules and limits
Northern VirginiaDominion Energy, PJMGS-5 class from Jan 1, 2027 for loads of 25 MW or more: minimum demand covers at least 85% of T&D and 60% of generation costs, 14-year contracts Inside Climate News on the SCC order, Nov 2025Ashburn grid connections 5 to 7 years DC Byte via DCK, Aug 5, 20260.3% (Q1 2026) CBRE, Jun 17, 2026Exemption active: $150M and 50 jobs, through Jun 30, 2035 VEDPLoudoun moved data centers to special exception on Mar 18, 2025 McGuireWoods, Apr 10, 2025Digital Gateway rezonings voided, upheld on appeal Mar 31, 2026 WTOP, Apr 2026
Columbus, OhioAEP Ohio, PJMData Center Tariff for loads of 25 MW or more: 85% minimum demand, ramp up to 4 years plus 8, exit fee of 36 months, 50% collateral AEP Ohio, in effect Jul 23, 2025Studied in tranches; the latest applications were due Sep 30, 2026 AEP Ohio0.1% JLL, Aug 11, 2026; JLL counts differently from CBRENot checked for this tableNot in our sources
AtlantaGeorgia PowerOver 100 MW: contracts up to 15 years with minimum billing, each reviewed by the PSC Georgia PSC, Jan 23, 2025Large-load pipeline grew from 12 GW to 36.5 GW during 2024 DatacenterDynamics, Jan 20251.0% (Q1 2026); 2,882 MW under construction, now CBRE's largest North American construction market CBRE, Jun 17 and Aug 27, 2026Exemption active, thresholds by county size; certificates expire Dec 31, 2031 Ga. Comp. R. & Regs. 560-12-2-.117Moratoriums in 2025 in Coweta, Clayton, Pike, Lamar and Troup Counties and LaGrange; Forsyth bars cooling from the county water system GPB, Oct 22, 2025
Dallas-Fort WorthERCOTBatch Zero study rules for loads of 75 MW or more approved Jun 18, 2026; SB 6 large-load rules due by Dec 2026 Utility Dive, Jun 22, 2026; Latitude Media, Dec 3, 2025More than 438 GW of large-load requests in the ERCOT queue; interconnection typically 2 to 4 years Utility Dive, Jun 22, 2026; ASHRAE1.8% (Q1 2026) CBRE, Jun 17, 2026Exemption active: $200M, 20 jobs, 10 or 15 years, state 6.25% only Texas Comptroller, Jul 27, 2026Not in our sources
West TexasERCOTSame ERCOT batch process as aboveSame ERCOT queue as aboveNot reported; 2.9 GW under construction (H2 2025) Cushman & Wakefield, Feb 26, 2026Same Texas program as aboveWater: 58.8% of Texas AI data centers sit in high water stress areas TRG Datacenters via DCK, Oct 12, 2026, vendor analysis
ChicagoComEd, PJMNot in our sourcesPower delivery timelines extend into 2032 or later CBRE, Jun 17, 20262.2% (Q1 2026); no contiguous 5 MW+ space available in 2026 CBRE, Jun 17 and Aug 27, 2026CBRE's H1 2026 Chicago page lists state incentives as paused CBRE, Aug 27, 2026Not in our sources
PhoenixAPS and SRPNot in our sourcesNot in our sourcesNot reported. 442 MW absorbed and 1.7 GW under construction in H1 2026 JLL, Aug 11, 2026260+ MW absorbed in H1 2026, average lease term 7 years CBRE, Aug 27, 2026June 2026 budget deal includes a three-year pause for new data centers AZFamily, Jun 9, 2026Phoenix has required a Special Permit since Jul 2, 2025 City of PhoenixTucson ended staff work on Project Blue Aug 6, 2025 AZFamily
Silicon ValleyPG&E and Silicon Valley PowerNot in our sourcesSome developers were told they would not get utility power for over a decade CBRE, Jun 24, 2024Asking rents for 10+ MW flat in H1 2026 CBRE, Aug 27, 2026Not checked for this tableNot in our sources

JLL and CBRE measure vacancy differently; compare figures from the same source only. Utility names without a source are given for orientation, not as a statement about capacity.

The national picture

  • Primary-market vacancy hit a record low of 1.4% in the first half of 2026, with 7,481 MW under construction and 80.4% of it preleased. CBRE North America Data Center Trends H1 2026, Aug 27, 2026
  • Less than 1,500 MW of future colocation capacity in primary markets was still uncommitted, roughly half a year of demand at the current pace. CBRE, Aug 27, 2026
  • JLL counted a record 25 GW absorbed in the first half of 2026 and expects vacancy near zero through 2028. JLL, Aug 11, 2026
  • Cushman & Wakefield does not expect meaningful easing before 2030. Cushman & Wakefield, Feb 26, 2026
  • On the supply side, 2,061 GW of generation and storage was waiting to connect at the end of 2025, and the median project took more than 5 years from request to operation. Lawrence Berkeley National Laboratory, Jul 1, 2026

How to use a market table on a real site

A market row tells you the odds, not the answer for a parcel. Two sites in the same county can sit on different substations with very different capacity. Use the table to decide where to file load requests, then score each site on what the utility tells you. The tariff section and the tax section on the home page explain how to score those criteria.

Leasing rather than building? Vacancy and asking rents matter more than tariffs. CBRE's asking rents for 250 to 500 kW in Northern Virginia ran $190 to $235 per kW per month in Q1 2026, and $200 to $230 in Chicago. CBRE, Jun 17, 2026 We place buyers in colocation and powered shells, and the facility pays our fee. Request a Site Review

What this table leaves out

We left out markets where our sources were too thin to fill most of a row, and figures we could not trace to a primary source. Water stress appears only where a dated source gave it. If you need a market that is not here, the site review request is the place to ask.

Questions about power by market

Where is power available for data centers right now?

Nowhere is it quick at scale. Published ranges run from typically 2 to 4 years for interconnection in Texas (ASHRAE) to 5 to 7 years for grid connections in Ashburn (DC Byte via Data Center Knowledge, Aug 5, 2026), and ComEd's delivery timelines in the Chicago market reach into 2032 or later (CBRE, Jun 17, 2026). Sites that can use existing grid capacity take about half as long as those needing new transmission (CBRE, Sep 9, 2024).

What is the data center vacancy rate in Northern Virginia?

CBRE put Northern Virginia vacancy at 0.3% in Q1 2026, down from 0.8% a year earlier (CBRE Global Data Center Trends 2026, Jun 17, 2026). Across primary North American markets, CBRE reported a record low of 1.4% in the first half of 2026.

Which states paused data center tax incentives?

Arizona's June 2026 budget deal includes a three-year pause on exemptions for new data centers (AZFamily, Jun 9, 2026). CBRE's first-half 2026 Chicago report lists Illinois incentives as paused. Texas, Virginia and Georgia programs remain open, with Georgia certificates expiring Dec 31, 2031.

Why do CBRE and JLL vacancy figures differ?

They measure different things. JLL includes owner-occupied and frontier capacity in its counts, so its figures should not be mixed with CBRE's in one comparison. The table names the source for every vacancy figure.

How often is this table updated?

We check it each quarter and after major tariff, tax or zoning decisions. The date at the top of the page shows the last check.