AI data center site selection

An AI training campus is chosen for its power date before anything else. This page covers how AI shifts the criteria, what large-load tariffs mean for a ramping GPU load, training against inference, and the federal bill that would end confidential AI site searches.

Sources rechecked in November 2026

How AI changes the weights

The scorer's AI training preset moves power availability from 25 to 35 of 100 and tariff terms from 10 to 12, and cuts latency from 5 to 2. Water rises to 9 because dense GPU halls usually need liquid cooling. Those are our judgments, labeled as such in the scorer, and you can change them.

  • Density. Equinix cites more than 100 kW per rack for NVIDIA DGX H100 deployments. Equinix blog, Aug 6, 2024, operator figure A site that suits 10 kW racks may need a different cooling plant, water supply and electrical design at that density.
  • Conversion delays. Converting an existing hall from air to liquid cooling can run over half a year late. CBRE North America Data Center Trends H1 2026, Aug 27, 2026
  • Scale. Texas regulators now study loads of 75 MW or more in batches, not one at a time. Utility Dive, Jun 22, 2026

Score My Sites on the AI preset

Training against inference

Training

Large, dense, latency-tolerant. Site for the earliest firm power at a tolerable tariff, cooling water or a low-water design, and room to add phases. Distance from users is a minor cost.

Inference and cloud regions

Smaller blocks closer to users and other regions. Score latency against a written budget and weight fiber diversity more heavily. At about 1 ms of round trip per 100 km of fiber route CommScope, 2017, a few hundred kilometers can decide whether a site works.

Large-load tariffs and a ramping GPU load

Utilities facing record requests now make large customers carry the cost of the capacity they reserve. For an AI load that ramps in phases, the minimum bill, the term and the collateral can matter more than the energy rate.

TariffApplies toMinimum billTermCollateral or costSource
AEP Ohio Data Center TariffLoads of 25 MW or more85% of the highest monthly billing demandRamp period of up to 4 years, plus 8 years; exit fee of 36 months of minimum charges50% of total minimum charges, unless rated A-/A3 with enough cashAEP Ohio tariff page (adopted Jul 9, 2025, in effect Jul 23, 2025)
Dominion Energy GS-5 class, VirginiaLoads of 25 MW or more at a 75% load factorAt least 85% of transmission and distribution and 60% of generation costs14-year contracts, starting Jan 1, 2027Not stated in our sourceInside Climate News on the Virginia SCC order (approved Nov 2025)
Georgia Power large-load ruleOver 100 MWMinimum billing in each contractUp to 15 years (was 5); each contract reviewed by the Georgia PSCSite-specific and upstream costs can be billed to the customerGeorgia PSC media advisory, Jan 23, 2025

In Texas, more than 438 GW of large-load requests sat in ERCOT's queue by June 2026, nearly 90% from data centers. Texas SB 6 also requires rules on disclosing duplicate interconnection requests and sharing costs, due by December 2026. Utility Dive, Jun 22, 2026; Latitude Media, Dec 3, 2025

Before you score cost and tariff terms, model the minimum bill against your realistic ramp, not the nameplate.

Behind-the-meter and bridge power

When the grid date is too late, some developers plan on-site generation to bridge the gap or to run the campus outright. A fuel cell maker projected that a third of campuses would be fully powered on site by 2030. Bloom Energy report, via The Register, Jan 20, 2026, vendor projection Treat that as a vendor's forecast. For scoring, on-site power changes the power question rather than removing it: score the fuel supply, the air permit and the date the plant can run, and keep the grid connection on the list.

Community and disclosure risk

AI projects draw the most local attention. In JLL's survey, 79% of Americans supported US leadership in AI, but only 14% supported a data center near them. JLL, Aug 11, 2026 Moratoriums, new special permit rules and court reversals all arrived in 2025 and 2026, as the permitting section on the home page lays out. Weight permitting accordingly, and check it again before you close.

H.R. 8488, the AI Data Center Site Selection Transparency Act

Status: proposed legislation. Introduced in the House on Apr 23, 2026 by Rep. LaMonica McIver of New Jersey and referred the same day to the Committee on Energy and Commerce. Ten cosponsors, all Democrats. No further action was recorded as of Nov 29, 2026. Bill text, GovInfo (BILLS-119hr8488ih); status from FastDemocracy and Quiver Quantitative bill trackers, checked Nov 29, 2026

What it would require of developers of AI-focused data centers

  • Public notice at least 180 days before a "definitive step," including the site, the resources the project would need and its environmental impact, sent to local elected officials and released to the public.
  • Definitive steps include binding land purchases or leases, binding utility power agreements, substantial on-site construction, final site plan or critical permit applications, and non-cancelable orders for long-lead equipment.
  • Limits on NDAs during siting, and no NDAs with government entities or about public resources.
  • An independent environmental analysis paid for by the developer, and outreach through local media, mail, signage and materials in more than one language.
  • Enforcement by the Federal Trade Commission, treating a violation as an unfair or deceptive practice.

Why it matters for a site search

Confidential searches under project code names are standard, because land prices and local politics shift once a buyer is known. If the bill became law in its current form, AI site searches would have to plan for a public notice window of six months before locking in land or power, and the community risk score would carry more weight. The bill sets no MW threshold. We will update this page if it moves.

Getting help with an AI site search

We review AI shortlists against the power, tariff and permitting criteria, run full site studies, and place AI buyers in colocation or powered shells with power on their date. If your search ends in a colocation lease or a powered shell that we place you in, the facility pays our fee. Site selection studies, shortlist reviews and land assessments are billed at a fixed fee that you sign off on in writing first; no paid work starts without it.

Request a Site Review Score My Sites

AI site selection questions

What is different about site selection for an AI data center?

Power dominates. Training clusters need very large, dense loads on a firm date, so power availability, tariff terms and cooling water outweigh latency, which barely matters for training. Inference sits closer to users and weighs latency and fiber more heavily.

Do AI training data centers need low latency?

Not to users. A training run moves data within the cluster, not across the country, so a training campus can sit far from population centers. Inference, which answers user requests, is a different case and should be scored with a latency budget.

What is the AI Data Center Site Selection Transparency Act?

H.R. 8488, introduced on Apr 23, 2026 by Rep. LaMonica McIver and referred to the House Committee on Energy and Commerce. It would require developers of AI-focused data centers to give public notice at least 180 days before a binding step such as a land purchase or a power agreement, limit NDAs during siting, and fund an independent environmental analysis, with the FTC enforcing it. As of November 2026 it had not moved past committee referral.

Can a data center developer use an NDA during site selection?

Under current federal law, yes, and confidential searches are standard practice. H.R. 8488 would limit NDAs during siting and bar them with government entities for AI-focused data centers, but it is proposed legislation, not law.

How do large-load tariffs affect AI projects?

They charge for reserved capacity whether or not it is used. AEP Ohio's data center tariff bills at least 85% of the highest monthly demand for the ramp period plus 8 years, and Dominion's GS-5 class uses 14-year contracts from 2027. A GPU deployment that ramps slower than planned pays for capacity it is not using.